Lead Mosque

Location Shkoder
Turnkey Project for the Supply and Installation of Hydraulic and Electrical Equipment at the Pumping Station

This turnkey project aims to protect and enhance the functionality of one of Shkodër’s most iconic historical monuments by implementing advanced technical systems:

Main objectives of the project:
1. Protection of the mosque from flooding by installing a submersible pump system with a “cooling jacket” to drain rainwater outside the mosque perimeter.
• Technical specifications: 3 x Submersible Pumps, 30 kW each, Flow rate: 150 l/s, Head: 12 m
2. Supply of sanitary water via a booster pump group installation;
3. Irrigation water pumping system;
4. Wastewater pumping system.