Shkopet HPP – Turbine Replacement
As part of the modernization of energy production capacities, Novamat has undertaken the project of replacing two existing turbines of 2 x 12 MW with two new turbines of 2 x 13.3 MW, along with all associated auxiliary systems.
The first phase of the project includes:
1. A complete audit and inspection of the current site conditions, equipment, and systems to be replaced;
2. Implementation of European HSE (Health, Safety, and Environment) standards;
3. Dynamic and static testing of the overhead crane with a load capacity of up to 63 tons to ensure safe and proper operation during equipment handling;
4. Dismantling of the existing turbines and their auxiliary systems, including generators, runners, DTL, filtration system, drainage pumps, and the discharge valves of the spiral casing and draft tube.
The first phase of the project includes:
1. A complete audit and inspection of the current site conditions, equipment, and systems to be replaced;
2. Implementation of European HSE (Health, Safety, and Environment) standards;
3. Dynamic and static testing of the overhead crane with a load capacity of up to 63 tons to ensure safe and proper operation during equipment handling;
4. Dismantling of the existing turbines and their auxiliary systems, including generators, runners, DTL, filtration system, drainage pumps, and the discharge valves of the spiral casing and draft tube.